Apr 1, 2021 | Construction Updates
In this week’s #BridgingForTheFuture progress update, crews have begun switching gears and started installation of the new high speed machinery gear boxes and line shafts as showcased in the featured photo. However, before doing so, significant time was spent to...
Mar 26, 2021 | Construction Updates
Today’s featured photo once again showcases the ongoing installation of the various low speed machinery components for both bridge spans. Next week, crews are expected to begin installation of select high speed machinery components that includes motor base...
Mar 18, 2021 | Construction Updates
This week’s featured image showcases one of the new navigational lights being installed which will operate between sunset and sunrise, or during times of restricted visibility, such as in fog or rain. These lights are one of the most important safety systems so...
Mar 11, 2021 | Construction Updates
Today’s #BridgingForTheFuture featured photo showcases some of the original and refurbished east span low speed machinery gears being re-installed this week by Landform Civil Infrastructure crews. Crews have also installed the electrical conduit and transfer...
Mar 4, 2021 | Construction Updates
Today’s #BridgingForTheFuture Throwback Thursday features a photo courtesy of Elgin County Archives and from the Ian D. Cameron Collection showcasing the coal-powered steamboat “Laura” navigating the inner harbour. Landform Civil Infrastructure crews...