Halfway there…!

Halfway there…!

This week marks approximately the halfway point in the rehabilitation of the #KingGeorgeVILiftBridge as we continue #BridgingForTheFuture! Despite its appearance and belief that the bridge rehabilitation project may soon be done, unfortunately there’s still a...
Paint Removal Preparation Underway

Paint Removal Preparation Underway

With all required concrete repairs and structural steel reinforcement substantially completed on the west bridge span, Landform Civil Infrastructure is now continuing with their paint removal preparations. Such preparations involve encapsulation of the bridge span...
All Way Stop! But Full Steam Ahead!

All Way Stop! But Full Steam Ahead!

With final restoration and installation of temporary signage associated with the Warren Street intersection improvements now complete, all road users are advised that both intersections are now currently controlled by all way stops, and will be enforced! Installation...

Rain and Concrete Placement

Despite the rain, crews carried on with intersection improvement construction work with the installation of new curbs along Colborne Street, and are planned for installation along Carlow Road tomorrow (weather permitting). Beginning today, weather permitting, final...