This week saw significant progress completed with concrete and asphalt placement by R.Russell Construction associated with the intersection turning lane and pedestrian crossover improvements along Colborne, Warren, and Carlow.  Next week crews aim to finish top coat asphalt placement along Carlow and at driveway aprons, installation of pedestrian crossover poles and signage, complete line painting, and begin final restoration.

Back at the #KingGeorgeVILiftBridge, Landform Civil Infrastructures Inc. focused on installing their suspended working platform under the west span, and began concrete removals and installing formwork for patch repairs. These works will continue while interior mechanical verification efforts also continue.

Are you wanting further details on work completed this past week… or wondering what is planned for next week…? To find out more, check out the Weekly Progress Report now available of the “Construction” webpage.